Côte d’Ivoire’s government says construction of Abidjan’s first metro line is about 66% complete, with commercial passenger service planned for January 2029. The target was announced by Prime Minister Robert Beugré Mambé during an inspection of the project on November 11.
The schedule remains a government target, not a guarantee that trains will begin carrying passengers on that date. The next major milestone is testing: the first on-site trials are planned for late 2028. Two trains intended for the tests are currently undergoing checks in Valenciennes, France, before being sent to Côte d’Ivoire, according to the Ivorian Press Agency.
A north-to-south route through seven communes
Line 1 is planned to run 37.4 kilometres between Anyama in the north and Port-Bouët in the south, connecting seven communes: Anyama, Abobo, Adjamé, Plateau, Treichville, Marcory and Port-Bouët. The route is expected to have 18 stations and provide a north–south rail corridor across Greater Abidjan.
The project is designed to address some of the pressure on daily travel in the country’s largest urban area. Government projections say the metro could serve about 540,000 passengers a day, using a fleet of 25 to 30 trains, each with capacity for around 1,300 passengers. These are planned capacities, not current passenger figures: the system is still under construction and has not begun operating.
Different parts of the work are progressing at different rates
The 66% figure is the government’s estimate of overall project execution. Progress varies by component. RTI, Côte d’Ivoire’s public broadcaster, reported that civil engineering and station construction were about 80% complete, while work on tracks and systems stood at around 55% during the prime minister’s inspection.
That gap highlights the amount of work still required beyond visible construction. A rail line must be fitted with tracks, signalling, power and other operating systems, then tested before it can safely carry passengers. The planned late-2028 trials will be an important stage in showing whether infrastructure and trains can operate together as intended. The authorities have not said that the testing period will itself be the start of public service; January 2029 remains the stated date for commercial operations.
The inspection included several project sites, among them the depot in Abobo-Sagbé and the Akwaba site in Port-Bouët. The depot is expected to house technical facilities needed to operate the line. Another major structure is a 506-metre viaduct above the Ébrié Lagoon, described by RTI as 11 metres wide and supported by 12 piers, seven of them in the lagoon.
Tests and operator preparations
Construction is only one part of opening a new rail service. The Ivorian Press Agency reported that Keolis Côte d’Ivoire has been mandated to operate and maintain Line 1. The company is preparing operating procedures and maintenance plans suited to local conditions, while a vocational training programme is being developed to prepare workers for operations and upkeep.
Two trains are being tested in Valenciennes, France, before their planned delivery to Côte d’Ivoire for local trials. According to the Ivorian Press Agency, the first on-site tests are expected at the end of 2028. Their outcomes, along with the completion of track and system work, will help determine whether the January 2029 opening target can be met.
Jobs and commercial activity around stations
The government is also presenting the metro as an employment and urban-development project. Beugré Mambé said more than 2,000 Ivorians were already working on the construction, and projected that the project would generate more than 5,000 jobs over time, including 2,000 permanent positions. These figures are government estimates.
Officials also want businesses to take part in commercial activity around the stations. The government says major stations will include spaces for retail and other services, and has invited capable Ivorian private operators to prepare for involvement. Station-area businesses could create new opportunities, though their eventual scale will depend on the facilities built and demand from passengers.
Line 1 is intended to complement a separate Bus Rapid Transit project on an east–west route between Bingerville and Yopougon. The two projects cover different corridors and modes of transport; together, they are expected to expand mass transit options across Greater Abidjan.
For now, the confirmed update is that the government estimates the metro line to be 66% complete and is targeting commercial service in January 2029. Late-2028 testing, the progress of track and systems installation, and preparations for operating the network will be key indicators of whether that timeline remains achievable.
The remaining track and systems work, delivery of trains and results of late-2028 testing will determine whether the target can be met.